Updates on The Gayle and Tom Benson Ochsner Children’s Hospital

This webpage is dedicated to keeping our neighbors informed about The Gayle and Tom Benson Ochsner Children’s Hospital. We’ll share project updates, upcoming work and other information that may be helpful to the surrounding community.

Read Press Release right_arrow_icon
Ochsner Childrens Hospital Exterior
down_caret_icon

Fall 2026 Ochsner Children's Update

Read the Update

Project Details

  • Green Space and Neighborhood Amenities Rendering Chevron Arrow

    As part of this project, Ochsner will develop a new neighborhood pocket park at River Road and Deckbar, providing green space for the community to enjoy. The project also includes a pedestrian crossing to the Mississippi River levee walking path, and enhanced landscaping and walkability along Deckbar. We’ve heard neighbors’ desires for more housing, retail, and food options in the area; and we are exploring how to develop the west side of Deckbar for these purposes in the future.

  • Trees Chevron Arrow

    • Ochsner has been working with professional arborists to create a plan that prioritizes maintaining trees and adding new trees.
    • The updated landscaping plan meets CPZ requirements.
    • Of the fourteen (14) oak trees that are on the site, eight (8) oak trees will not be impacted by this project.
    • Six (6) oak trees will be removed and replaced with six (6) substantial, 12-inch oak trees.
    • The historic oak tree, sometimes referred to as Big Betz, will be protected in the future.

    The trees that must be removed will be replaced with mature 12-inch oak trees, like this one.

  • Drainage Chevron Arrow

    • The proposed drainage improvements associated with the Children's hospital project will add significant subsurface storage on the south side of Jefferson Hwy.
    • The proposed drainage improvements exceed Jefferson Parish requirements and provide benefit to the surrounding areas.
    • Combined, the increased culvert capacity and the added subsurface detention system capacity will retain 435,433 gallons below grade (underground) and reduce peak flow runoff at Area Outfall 1 by approx. 52% and Area Outfall 2 by approx. 9.3%.
    • An example of this volume of retainage would be roughly 1 foot over the area of a football field.
    • By holding a significant amount of rainwater underground on our campus, we are slowing the flow into the drainage system to prevent flooding.
  • Traffic Chevron Arrow

    • The updated traffic plan was developed in consultation with Department of Transportation and Development (DOTD) and was awarded a letter of compliance from DOTD.
    • To ensure efficient traffic flow, Deckbar will be widened, and a series of new turn lanes will be incorporated at the intersections of Jefferson Highway and Deckbar as well as River Road and Deckbar.
    • The traffic analysis evaluated numerous scenarios (time of day, timing of signals, volume of cars, etc.) to create the best traffic plan.
    • The plan contemplates the projected volume of car trips once the project is complete.